Show/Hide Toolbars

Jim2® Business Engine Help File

Start by adding a new Contract Status.

 

pendfinish

 

Then, set the child machine that is due to be Finished to this new Status.

 

pendfinish1

 

Now on the master, go to the Linked Machines tab, find machines on PendFINISH, right click and select Finish on Variation.

 

linked machine

 

When you the Variation to the New Meter/Contract setup, the differences will show that machines set to Finish on Variation show as Removed

 

view variation

 

Then a quick check of the PendFINISH Machine to see it is now at FINISH.

 

Further information

Contract Variations