Finish Child on Master

Back Top Previous Next

Start by adding a new Contract Status.

 

pendfinish

 

Then, set the child contract that is due to be Finished to this new Status.

 

pendfinish1

 

Now on the master, go to the Linked Contracts tab, find contracts on PendFINISH, right click and select Finish on Variation.

 

linkedcontracts

 

When you the Variation to the New Meter/Contract setup, the differences will show that contracts set to Finish on Variation show as Removed

 

view variation

 

Then a quick check of the PendFINISH contract to see it is now at FINISH.

 