3 Tier Colour Billing

Back Top Previous Next

Prior to setting up 3 tier colour coverage billing, on the ribbon, go to Tools > Options > Purchase and tick Allow linking to Invoiced Jobs at $0 price:

 

linktoinvoice

 

A contract with 3 meters for colour page counts based on coverage (low, medium and high), plus a fourth meter for black.

 

Info

Separate stock codes are required for each meter setup. Jim2 does not allow duplicate stock codes in a meter setup.

 

Stock must be set up prior to adding meters, including macro descriptions on the Contracts tab.

 

Example Macros

{{Project.Meter.Counter Name" "}}{{"Last Read – "Project.Meter.Job.Previous Job.Meter Read" "}}{{"Last Estimated Read – "Project.Meter.Job.Previous Job.Estimated Meter Read" "}}{{Project.Meter.Job.Previous Job.Date Due" "}}{{"Current Read – "Project.Meter.Job.Meter Read" "}}{{"Estimated Read – "Project.Meter.Job.Estimated Meter Read" "}}{{"Prints – "Project.Meter.Job.Qty" "}}{{"Estimated Prints – "Project.Meter.Job.Estimated Qty" "}}

 

Users need to set the colour coverage level percentages at the contract itself, and turn the three meters to on. Each meter needs its own stock code (see image below), and on the Contracts tab of the consumable stock (not the meter stock), Yield must be entered (this is a percentage). An example might be:

Tier 1 Yield 5%

Tier 2 Yield 15%

Tier 3 Yield 50%

 

The contract will provide the three meter page counts.

 

3 tier meter setup

 

Customers receive an invoice showing CPC for each different meter, the number of pages for each meter, and a total cost for all three colour meters, as well as the black meter, and the resulting job:

 

3 tier billing

 

Further Information

3 Tier Colour Coverage Billing

3 Tier Colour Coverage Reads Billed with Total Colour Rate

3 Tier Colour Coverage Reads Min Volume on Colour Total

Set up Consumable Coverage on 3 Tier Billing Stock