Add an Expense PO to the same vendor, using the same invoice number and invoice date.
In the grid, select a 5-XXXX account (it does not matter which account as the transaction won't report to it – it is just a mandatory field on expense POs).
In the PO field at the left, enter the incorrectly finished PO number – you are linking the expense PO back to the PO to update the COGS for the stock on that PO.
Qty = 1
Enter the invoice price/total
You only need one line and a quantity of one, as Jim2 does the rest for you |
Finish and Save.
You will now have an invoice owing in creditors, and the COGS field on the original PO will be populated instead of 0.
Further information: